Materials Procurement Plan

The Material Procurement is planned in stages, as detailed below:

Stage 1 : Identification of Vendor for each product

  • Materials selected from the approved list of makes
  • Evaluation of Technical Compatibility based on Consultant's specification
  • Negotiations conducted for Commercial Pricing and Terms / Conditions
  • Freezing of final Vendor

Stage 2 : Securing Client approval for Product

  • Submission of makes of materials proposed to be used for Client approval
  • Submission of Samples / Sample Board for Client approval

Stage 3 : Quantity Survey

  • Obtaining approval of Shop Drawings
  • Quantifying material requirement based on the above
  • Preparing Schedules of Material requirements
  • Transcribing these schedules to the BOQ and evaluating project cost based on the Shop drawings as compared to Tender drawings
  • Communicating budgetary project cost
  • Obtain Client approval in case budgets are exceeded

Stage 4 : Material Procurement

  • Place Purchase Orders
  • Obtain drawings for client approval

Stage 5 : Quality Control : Please refer : Methodology for Quality Control

Stage 6 : Materials handling at site

  • Maintain Storage Yard for heavy materials and Stores for costlier / smaller materials
  • Maintain Registers for Stock
  • Security for Stock
  • Registers for Materials in / Out
  • Getting Security clearance from Client for In / Out materials
  • Disposal of Scrap on periodical basis keeping in view the segregation of usable / unusable / Toxic Scrap

Stage 7 : Communicating with Client the information on Material procurement :

To be done periodically till site closure

Stage 8 : Closing site and removal of excess material

  • Quantify materials excess
  • Tally with Billing / Delivery Challans
  • Submit list for Client approval and issue of Gate Pass
  • Clear materials and restore stock area to original condition for handing over to Client.